A TV 2 mapping identifies 57 data centre projects around Copenhagen, out of 111 recorded across Denmark. The tally does not mean that 57 new facilities have opened or that every planned development will be built.
The report by TV 2 Kosmopol covers the regional broadcaster’s area. TV 2 compiled its nationwide survey from a data extract supplied by DataCenterMap and then added its own research.
A quarter of projects are linked to technology giants
About a quarter of the 111 projects nationwide are associated with large technology companies such as Apple, Google, Meta and Microsoft, according to TV 2. That proportion concerns the number of projects, not their share of computing capacity or electricity use.
The broadcaster reports that these companies typically build the largest facilities, but says there is no public breakdown of their share of total Danish data centre capacity. The map therefore cannot establish their overall capacity share simply by counting sites.
Data centre projects face uncertainty before grid connection
The Danish Energy Agency (Energistyrelsen) also accounts for the risk that projects will not proceed. Its October 2026 sector note on data centres explains how it weights projects in Energinet’s electricity-connection pipeline according to their stage of development.
Projects move from initial discussions through screening and development to a connection agreement and, eventually, connection to the grid. The agency observes projects dropping out before that final stage, so it does not assume that every application will translate into operating capacity. This forecasting method is distinct from TV 2’s count of projects.
The regional mapping adds a local picture to the wider Nordic debate over access to electricity previously covered by NordiskPost.
Parliament will debate a proposed pause in new permits
In the Danish Parliament (Folketinget), the Red-Green Alliance (Enhedslisten) has proposed a temporary halt to new data centre permits. Proposal B 39, introduced on 23 October, would require the government to introduce the pause by 1 February 2027, pending parliamentary adoption of a national strategy.
The proposed strategy would address location, resource use, digital sovereignty, security of supply and the relationship with neighbouring communities. This remains a proposal, rather than an adopted moratorium. Parliament’s published timetable schedules its first reading for 19 November.